Tila HydroPower Project #2

 

Name

Tila Hydroelectric Project 2

Location

Nepal, Kalikot (Tila River)

Capacity

420MW (105MW x 4Set)

Generation

1,723GWh(46.8%)

Cost

USD 534.8M

 

Civil Work

DAM-74mH x 203.4mL

Feeder Tunnel-Φ4.1mD x (151, 186)mL x 2nos

Desilting Basin-260mL x 11mW x 17.5mH x 2chamber

Headrace Tunnel-13.44km (Φ5.5mD, Horse Shoe Shape)

Surge Shaft-Φ10mD x 103mH

Pressure Shaft-Φ2.85mD x 828mL x 2nos

Powerhouse Cavern-19.5mL x 125.5mW x 42.5mH

Transformer  Hall-15.5mL x 119mW x 21.2mH

Collection Gallery-N/A

Tailrace Tunnel-186mL x 6mW x 5mH (D-shape)

 

Electro Mechanical Equipment

Turbine-105MW x 4Set (Pelton, 375rpm)

Install Capacity-420MW

Energy Generated-1,723GW (46.8%)

Transmission Line-15km(220KV to Tila-1)

 

Layout

 

 

 

 

 

Tila-1

Financial IRR

17.01%

 

FIRR Equity

26.23%

 

Benefit / Cost Ratio

1.57

Preliminary Works

2.0 Year

 

Construction of Civil and E&M Works Period

4.5 Years